2024 Highway 78 Fiber Project Special Use
Placement of buried (2) 1.50-inch duct containing 288ct fiber optic cable via plow and directional bore at a depth of 36 inches and a crossing at a depth of 48 inches with handhole placements.
Project Summary
Location Summary:
Project is located along Highway 78 T16S R9E Sec 12 and T16S R10E Sec 7.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/28/2025 |
Decision | 05/2025 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Shoal Creek Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
2024 Highway 78 Fiber Project Special Use
Decision Signed Date: 05/29/2025
Forests:
National Forests in Alabama
Districts:
Shoal Creek Ranger District
States:
Alabama
Counties:
Clay
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gregory Scull
45 Highway 281
Heflin, AL 36264
256-463-2273